Question: A production manager must determine the processing sequence for seven jobs through the grinding and de-burring departments. The same sequence will be followed in each
.png)
a. Prepare a schedule using the SPT priority rule for the grinding department (using tire grinding times).
b. What is tire total flow time in the grinding department for the SPT sequence? What is tire make-span for the seven jobs in both the grinding and de-burring departments (using tire sequence found in part a)?
c. Determine a sequence that will minimize tire make-span in both departments. What total flow time will result for tire grinding department?
PROCESSING TIME (HOURS) Job orinding Deburring
Step by Step Solution
3.40 Rating (159 Votes )
There are 3 Steps involved in it
a Using Grinding times the SPT sequence is CBADGFE SPT Grinding Deburring Job Start Finish S... View full answer