Question: ) Use MS Project software to create a Gantt chart for the project. (5 points) a. Define project start date: Start Project September 9th, 2019.
) Use MS Project software to create a Gantt chart for the project. (5 points)
a. Define project start date: Start Project September 9th, 2019.
b. Define working hours: Monday-Friday 8:00am-5:00pm with 1 hour lunch break and Saturday 8:00am-12:00pm
c. Enter given task names.
d. Enter durations of the tasks.
e. Establish linkages for the tasks.
f. Automatically schedule the tasks
g. Manually enter the following requirement
Paint Task Start no earlier than 10/1/2019
Id Description Predecessor Time(Days)
| A | prepare site | none | 2 |
| B | pour foundation | A | 3 |
| c | Erect frame | B | 4 |
| d | Roof | C | 4 |
| e | windows | C | 1 |
| f | doors | C | 1 |
| g | electrical | C | 3 |
| h | Rough-in-frame | D,E,F,G | 2 |
| i | Door opener | F,G | 1 |
| j | paint | H,I | 2 |
| k | cleanup | J | 1 |