Question: ) Use MS Project software to create a Gantt chart for the project. (5 points) a. Define project start date: Start Project September 9th, 2019.

) Use MS Project software to create a Gantt chart for the project. (5 points)

a. Define project start date: Start Project September 9th, 2019.

b. Define working hours: Monday-Friday 8:00am-5:00pm with 1 hour lunch break and Saturday 8:00am-12:00pm

c. Enter given task names.

d. Enter durations of the tasks.

e. Establish linkages for the tasks.

f. Automatically schedule the tasks

g. Manually enter the following requirement

Paint Task Start no earlier than 10/1/2019

Id Description Predecessor Time(Days)

A prepare site none 2
B pour foundation A 3
c Erect frame B 4
d Roof C 4
e windows C 1
f doors C 1
g electrical C 3
h Rough-in-frame D,E,F,G 2
i Door opener F,G 1
j paint H,I 2
k cleanup J 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!