Question: Use Project Libre or Microsoft Project software to create a Gantt chart for the project. Define project start date: Start Project September 9 th ,
Use Project Libre or Microsoft Project software to create a Gantt chart for the project.
- Define project start date: Start Project September 9th, 2019.
- Define working hours: Monday-Friday 8:00am-5:00pm with 1 hour lunch break and Saturday 8:00am-12:00pm
- Enter given task names.
- Enter durations of the tasks.
- Establish linkages for the tasks.
- Automatically schedule the tasks
- Manually enter the following requirement
- Paint Task Start no earlier than 10/1/2019
| ID | Description | Predecessor | Time(Days) |
| A | Prepare site | None | 2 |
| B | Pour foundation | A | 3 |
| C | Erect frame | B | 4 |
| D | Roof | C | 4 |
| E | Windows | C | 1 |
| F | Doors | C | 1 |
| G | Electrical | C | 3 |
| H | Rough-in frame | D, E, F, G | 2 |
| I | Door opener | F, G | 1 |
| J | Paint | H, I | 2 |
| K | Cleanup | J | 1 |