Question: Use the below project info to answer the questions. ACTIVITY NORMAL TIME ( WEEKS ) NORMAL COST CRASH TIME ( WEEKS ) CRASH COST IMMEDIATE
Use the below project info to answer the questions.
ACTIVITY NORMAL TIME
WEEKS NORMAL
COST CRASH TIME
WEEKS CRASH
COST IMMEDIATE
PREDECESSORS
A $ $
B A
C A
D A
E B
F D
G C E F
Fill in the table to specify the crashing steps needed to minimize the cost of crashing to various project durations. Use project lengths of and weeks. For each project length, identify the length of each of the corresponding paths, specify which activity would have been crashed to achieve that project length duration is the starting point, so no activity needed to be crashed and calculate the crashing and total costs as shown in the table below.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
