Question: Use the below project info to answer the questions. ACTIVITY NORMAL TIME ( WEEKS ) NORMAL COST CRASH TIME ( WEEKS ) CRASH COST IMMEDIATE

Use the below project info to answer the questions.
ACTIVITY NORMAL TIME
(WEEKS) NORMAL
COST CRASH TIME
(WEEKS) CRASH
COST IMMEDIATE
PREDECESSORS
A 2 $ 501 $ 70
B 4802160 A
C 8704110 A
D 660580 A
E 71006130 B
F 4403100 D
G 51004150 C, E, F
Fill in the table to specify the crashing steps needed to minimize the cost of crashing to various project durations. Use project lengths of 18,17,16,15,14, and 13 weeks. For each project length, identify the length of each of the corresponding paths, specify which activity would have been crashed to achieve that project length (duration 18 is the starting point, so no activity needed to be crashed), and calculate the crashing and total costs as shown in the table below.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!