Question: Use the below table and answer the questions associated with it. (50 marks) Activity Initial Node Final Node Estimated Duration A 1 2 1 B
Use the below table and answer the questions associated with it. (50 marks) Activity Initial Node Final Node Estimated Duration A 1 2 1 B 1 3 2 C 1 4 3 D 2 5 4 E 3 5 5 F 3 6 4 G 4 7 6 H 5 6 6 I 7 6 2 J 6 8 3
a. Draw an AOA diagram. 5 marks b. Identify all paths in the network diagram with their durations. 5 marks
c. What is the critical path for this project? 5 marks
d. What is the earliest possible time to finish the project? 5 marks
e. Find the slack time for each activity. 10 marks
f. If task G was delayed by 1 days, how will this affect the project critical tasks and the project finish time? 5 marks
g. If task H was delayed by 3 days, what will be the impact of that delay on the project finish time? 5 marks
h. Use Project Plan 365 to produce the Gantt chart & network diagram of the project.