Question: Using Figure 6-2 on page 280, enter the activities, their durations (in days) and their relationships in Project 2016. Us a project start date of
Using Figure 6-2 on page 280, enter the activities, their durations (in days) and their relationships in Project 2016. Us a project start date of March 26, 2018. View the network diagram. Click the View tab and then click the Tables button under the Data group and then select Schedule. Write a few paragraphs explaining what the network diagram and schedule table show about Project Xs schedule? (25 points) Table 6-2 Network diagram data for a small project Activity Initial Node Final Node Estimated Duration 1 2 2 B 2 3 2 2 4 3 List and briefly describe the main processes involved in project schedule management. (5 points) What are milestones? Describe. (5 points) What is a network diagram? Describe two network diagramming methods. (5 points) Describe critical path analysis. How is the critical path calculated? (5 points) What is the Theory of Constraints? Describe critical chain scheduling, an application of the Theory of Constraints. (5 points) please cite any source 

Table 6-2 Network diagram data for a small project Activity Initial Node Final Node Estimated Duration 1 2 2 B 2 3 2 2 4 3 2 5 4 E 3 6 2 F 4 6 3 G 5 7 6 H 6 8 2 6 7 5 J 7 8 1 8 9 N Table 6-2 Network diagram data for a small project Activity Initial Node Final Node Estimated Duration 1 2 2 B 2 3 2 2 4 3 2 5 4 E 3 6 2 F 4 6 3 G 5 7 6 H 6 8 2 6 7 5 J 7 8 1 8 9 N Table 6-2 Network diagram data for a small project Activity Initial Node Final Node Estimated Duration 1 2 2 B 2 3 2 2 4 3 2 5 4 E 3 6 2 F 4 6 3 G 5 7 6 H 6 8 2 6 7 5 J 7 8 1 8 9 N Table 6-2 Network diagram data for a small project Activity Initial Node Final Node Estimated Duration 1 2 2 B 2 3 2 2 4 3 2 5 4 E 3 6 2 F 4 6 3 G 5 7 6 H 6 8 2 6 7 5 J 7 8 1 8 9 N
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts