Question: Draw the AON and use the Critical path method to compute the CP, and total slack. Use PERT to analyze the chance the delays on

Draw the AON and use the Critical path method to compute the CP, and total slack.

  • Use PERT to analyze the chance the delays on CP activities does not push the project duration beyond 35 days.

                       x: is a last digit of your roll number

                       y: is a # of sibilings (0,1…….)

                        z: is a last digit of your mobile number

                                                                   

Activity
predecessors
 
Optimistic
Most likely
Pessimistic
A
-
5
6
8
B
-
3
4
5
C
A
2
3
4
D
B
x-1
x +4
x+2
E
B
1
3
4
F
-
8
10 -z
15-z
G
E,F
2
3
4
H
C,D
2+x
2+y
2+z

Step by Step Solution

3.39 Rating (158 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Computer Engineering Questions!