Question: Draw the AON and use the Critical path method to compute the CP, and total slack. Use PERT to analyze the chance the delays on
Draw the AON and use the Critical path method to compute the CP, and total slack.
- Use PERT to analyze the chance the delays on CP activities does not push the project duration beyond 35 days.
x: is a last digit of your roll number
y: is a # of sibilings (0,1…….)
z: is a last digit of your mobile number
| Activity | predecessors | Optimistic | Most likely | Pessimistic |
| A | - | 5 | 6 | 8 |
| B | - | 3 | 4 | 5 |
| C | A | 2 | 3 | 4 |
| D | B | x-1 | x +4 | x+2 |
| E | B | 1 | 3 | 4 |
| F | - | 8 | 10 -z | 15-z |
| G | E,F | 2 | 3 | 4 |
| H | C,D | 2+x | 2+y | 2+z |