Question: Use the data below for problems 6 to 10. Year Proj Y Proj Z 0 ($210,000) ($210,000) 1 200,000 95,000 2 95,000 78,000 3 73,000
Use the data below for problems 6 to 10.
Year
Proj Y
Proj Z
0
($210,000)
($210,000)
1
200,000
95,000
2
95,000
78,000
3
73,000
4
87,500
The projects provide a necessary service, so whichever one is selected is expected to be repeated into the foreseeable future.Both projects have an 11% cost of capital.
6.What is each project's initial NPV without replication?
7.What is each project's equivalent annual annuity?
8.Now apply the replacement chain approach to determine the shorter projects' extended NPV.Which project should be chosen?
9.Now assume that the cost to replicate Project Y in 2 years will increase to $140,000 because of inflationary pressures.How should the analysis be handlednow, and which project should be chosen?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
