Question: Use the data in the activity table to answer the questions below: ACTIVITY Immediate Predecessor Normal Duration (wks) Minimum Duration (wks) Crash Costs ($/wk) A
Use the data in the activity table to answer the questions below:
|
ACTIVITY |
Immediate Predecessor |
Normal Duration (wks) |
Minimum Duration (wks) |
Crash Costs ($/wk) |
|
A |
--- |
5 |
5 |
--- |
|
B |
--- |
4 |
2 |
100 |
|
C |
A, B |
5 |
3 |
200 |
|
D |
C |
4 |
4 |
--- |
|
E |
C |
1 |
1 |
300 |
|
F |
C |
1 |
1 |
--- |
|
G |
D |
3 |
2 |
200 |
|
H |
E |
2 |
1 |
300 |
|
I |
F |
1 |
1 |
--- |
|
J |
H, I |
3 |
1 |
100 |
What is the slack time for Activity I and the early finish for Activity I?