Question: Use the diagram below to answer Question 32 - 36. Week 1 2 3 DC A Planned order release 100 100 100 DC B Planned

Use the diagram below to answer Question 32 - 36.

Use the diagram below to answer Question 32 - 36. Week 1 2 3 DC A Planned order release 100 100 100 DC B Planned order release 200 100 Central Supply - Lead time 2 weeks Order Quantity : 500 units Week 1 2 3 300 200 400 400 Gross requirements Projected Available Balance 500 Planned order receipts Planned order release 500 What is the Projected Available Balance at Central Supply in Week 2? O a. 100 b. 200 O c. 300 O d. 400