Question: Use the failure probability and consequence scores shown in thetable to determine the risk factorfor the project. Maturity 0.2 Cost 0.5 Complexity 0.5 Schedule 0.1
Use the failure probability and consequence scores shown in thetable to determine the risk factorfor the project.
Maturity 0.2
Cost 0.5
Complexity 0.5
Schedule 0.1
Dependency 0.4
Reliability 0.2
Performance0.1