Question: Use the following information for Question #1 and 2. Given the following project information, answer the following questions, assuming the project timeline is 6 months.

Use the following information for Question #1 and

Use the following information for Question #1 and 2. Given the following project information, answer the following questions, assuming the project timeline is 6 months. PV = $125,000 EV = $100,000 AC = $150,000 BAC = $200,000 Question 1 For the project: A) What is the cost variance? B) What is the schedule variance? C) What is the cost performance index (CPI)? Round to two decimal places. D) What is the schedule performance index (SPI)? Round to two decimal places. Show your calculations

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock