Question: Use the following information to perform an earned value analysis. Activity Budget Percent Scheduled PV Percent Complete EV AC A 200 100 100 200 B

Use the following information to perform an

Use the following information to perform an earned value analysis. Activity Budget Percent Scheduled PV Percent Complete EV AC A 200 100 100 200 B 600 50 100 500 500 50 50 350 D 400 100 100 400 E 500 50 75 250 F 160 50 75 180 G 300 50 25 100 H 140 0 O o o 200 0 o a. Complete the PV column. b. Complete the EV column. c. What is the value of the work remaining on the project? d. What is the CPlas of the status date? e. What is the SPI as of the status date

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!