Question: Use the following information to perform an earned value analysis. Activity Budget Percent Scheduled PV Percent Complete EV AC A . 200 100 100 200

Use the following information to perform an

Use the following information to perform an earned value analysis. Activity Budget Percent Scheduled PV Percent Complete EV AC A . 200 100 100 200 B 600 50 100 500 500 50 50 350 D 400 100 100 400 E 500 50 75 250 F 160 50 75 180 G 300 50 25 100 H 140 0 0 0 1 200 0 0 0 3000 1980 a. Complete the PV column. b. Complete the EV column. c. What is the value of the work remaining on the project? d. What is the CPI as of the status date? e. What is the SPI as of the status date