Question: 5) Use the following project information Activity Optimistic Time Estimate (weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 3 6
5)
Use the following project information
| Activity | Optimistic Time Estimate (weeks) | Most Likely Time Estimates (weeks) | Pessimistic Time Estimates (weeks) | Immediate Predecessor(s) |
| A | 3 | 6 | 9 | none |
| B | 3 | 5 | 7 | A |
| C | 4 | 7 | 12 | A |
| D | 4 | 8 | 10 | B |
| E | 5 | 10 | 16 | C |
| F | 3 | 4 | 5 | D, E |
| G | 3 | 6 | 8 | D, E |
| H | 5 | 6 | 10 | F |
| I | 5 | 8 | 11 | G |
| J | 3 | 3 | 3 | H, I |
- construct a network diagram using AON notation.
- calculate the expected time for each of the project activities.
- calculate the variance for each of the project activities
- calculate the completion time for this project.
- Identify the activities included on the critical path of this project.
- Calculate the probability that the project will be completed in 38 weeks.
- Calculate the probability that the project will be completed in 42 weeks.
*Please answer all questions and show ALL work*