Question: Use the graph below to answer this question ACTIVITY PREDECESSOR NORMAL TIME NORMAL COST CRASH TIME CRASH COST A - 7 days $6,000 6 days

Use the graph below to answer this question

ACTIVITY

PREDECESSOR

NORMAL TIME

NORMAL COST

CRASH TIME

CRASH COST

A

-

7 days

$6,000

6 days

$6,600

B

A

4 days

$1,200

2 days

$3,000

C

B

11 days

$4,000

9 days

$6,000

a. What action is the least expensive if you were to crash and reduce the critical path by 1 day/

b. Assuming no other paths are critical, what would you do to reduce the critical path by one additional day - the least expensive action?

c. What is the total cost of this 2-day reduction?

Group of answer choices

a: Reduce a = $600; b: Reduce b & c = $1900; c: Total Cost = $2500

a: Reduce a = $600; b: Reduce b = $900; c: Total Cost = $1500

a: Reduce a = $600; b: Reduce b = $1800; c: Total Cost = $2400

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!