Question: Use the information below to answer this question and the next two.You run two machines A and B in sequence to produce your product. Machine

Use the information below to answer this question and the next two.You run two machines A and B in sequence to produce your product. Machine A has a run time of 5 minutes and Machine B has a run time of 10 minutes.Which machine is the bottleneck?Machine AMachine BCannot be determined