Use the information contained below to calculate the total normal cost of the project.

Activity ID Slope Max crash time Normal Time Normal Cost Crash Time Crash Cost
A $80.00 2 8 $40 6 $200
B $20.00 2 5 $80 3 $120
C $50.00 2 12 $50 10 $150
D $100.00 1 14 $100 13 $200
E $40.00 1 4 $60 3 $100
F $0.00 0 3 $120 3 $120