Question: Use the table below to calculate the total normal cost of the project: Activity ID Slope Max crash time Normal Time Normal Cost Crash Time

Use the table below to calculate the total normal cost of the project:

Activity ID Slope Max crash time Normal Time Normal Cost Crash Time Crash Cost
A $80 2 8 $40 6 $200
B $20 2 5 $80 3 $120
C $50 2 12 $50 10 $150
D $100 1 14 $100 13 $200
E $40 1 4 $60 3 $100
F $0 0 3 $120 3 $120