Question: Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash

Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost.

Note: Choose B instead of C and E (equal costs) because it is usually smarter to crash early rather than late AND one activity instead of two activities

3. Use the information contained below to compress one time unit per move using the least cost method. Assume the total indirect cost for the project is $700 and there is a savings of $50 per time unit reduced. Record the total direct, indirect, and project costs for each duration. What is the optimum cost-time schedule for the project? What is the cost?

Note: The correct normal project duration and total direct cost are Use the information contained below to compress one time unit per move

ject duration 14 tal direct cost 1,200

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!