Question: Use the information contained below to compress one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point
Use the information contained below to compress one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed and the adjusted total cost.
| Activity | Crash cost | Maximum | ||
| ID | (Slope) | Crash Time | Normal time | Normal cost |
| A | 0 | 2 | 150 | |
| B | 100 | 1 | 3 | 100 |
| C | 50 | 2 | 6 | 200 |
| D | 40 | 1 | 4 | 200 |
| E | 55 | 1 | 3 | 200 |
| F | 0 | 1 | 150 | |
| Total direct normal costs | $1,000 | |||
Compress from time period 13 to time 12 crash the following activity(s)
Compress from time period 12 to time 11 crash the following activity(s)
Compress from time period 11 to time 10 crash the following activity(s)
What is the crash point of the network?
| |||||||||