Question: Use the information contained below to create a network diagram. Then compress one-time unit per move using the least cost method. Reduce the schedule until

Use the information contained below to create a network diagram. Then compress one-time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost.

  1. Create a network diagram
  2. Calculate paths and identify the critical path
  3. Create a table that calculates crash costs and adjusted total costs with headings: Activity. Norm Duration, Norm Cost, Max Crash, Slope, Crash Cost, Adj Total Costs, in that order.
  4. Identify the activity at each step that was crashed, number of crash steps, and total costs

Submit your Excel workbook to the link in this assignment by the deadline.

Activity

Preceding Activity

Normal Duration

Normal Cost

Max Crash

Crash cost/Slope

A

None

2

150

1

100

B

A

3

100

1

80

C

B

2

200

1

60

D

B

5

200

1

40

E

A

5

200

2

40

F

C

3

150

2

40

G

D

5

200

1

20

H

E, F, G

1

200

0

0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!