Question: Use the information in the table to determine the early finish time for Activity D . table [ [ Task , Predecessor,Duration, table

Use the information in the table to determine the early finish time for Activity D.
\table[[Task,Predecessor,Duration,\table[[Early],[Start]],\table[[Early],[Finish]],\table[[Late],[Start]],\table[[Late],[Finish]]],[A,-,8,,,,],[B,A,,,,14,],[D,A,,,23,8,],[E,C B,6,23,,26,],[F,C,,,32,,]]
Select one:
A. Day 32
B. Day 23
C. Day 26
D. Day 29
 Use the information in the table to determine the early finish