Question: Use the information provided in Table 1 to answer the following questions: Table 1 . Activity IP a m b TE Variance SD A 1

Use the information provided in Table 1 to answer the following questions:
Table 1.
Activity IP a m b TE Variance SD
A1-6714
A2-51015
A3 A1345
A4 A1, A24512
A5 A1, A24710
A6 A34512
A7 A4, A63711
A8 A5, A761116
1. Complete the information in Table 1TE, Variance, and SD
2. Which activities are on the critical path?
3. What is the critical path probability the project will be completed within 39 days?
4. What is the project completion time corresponding to a 96% probability?