Question: Use the information provided in Table 1 to answer the following questions: Table 1 . Activity IP a m b TE Variance SD A 1
Use the information provided in Table to answer the following questions:
Table
Activity IP a m b TE Variance SD
A
A
A A
A A A
A A A
A A
A A A
A A A
Complete the information in Table TE Variance, and SD
Which activities are on the critical path?
What is the critical path probability the project will be completed within days?
What is the project completion time corresponding to a probability?