Question: Use the longest task time heuristic. 4-a balance the line with Cycle time = 1.3 minute Task and time A, 0.2 B, 0.4 C, 0.3
Use the longest task time heuristic.
4-a balance the line with Cycle time = 1.3 minute
| Task and time |
|
| A, 0.2 |
|
| B, 0.4 |
|
| C, 0.3 |
|
| D, 1.3 |
|
| E, 0.1 |
|
| F, 0.8 |
|
| G, 0.3 |
|
| H, 1.2
|
|
| Work Station | Eligible | Assigned task | Assigned Time | Remaining Time |