Question: Use the longest work element rule to balance the assembly line described in the following table and figure below so that it will produce 50
Use the longest work element rule to balance the assembly line described in the following table and figure below so that it will produce 50 units per hour.
a. What is the cycle time?
b. What is the theoretical minimum number of workstations?
c. Which work elements are assigned to each workstation?
d. What are the resulting efficiency and balance delay percentages?
e. Use the shortest work element rule to balance the assembly line. Do you note any changes in the solution?
A 32 65 80. 20 08 20 F 12 E D 16 45 & 35 60 H 10 K 10 Work Element ABCDEFGHI C K Total Time (sec) Immediate Predecessor(s) 32 20 65 16 45 12 20 10 60 35 10 325 None AABCC D, E F G J, H, I
Step by Step Solution
3.41 Rating (154 Votes )
There are 3 Steps involved in it
Solution a Cycle time Demand 50 units per hour Time foe one unit 6050 min or 606050 sec 72 sec Cycle ... View full answer