Question: Use the minimum slack heuristic to develop a resource schedule; use the smallest duration and then lowest activity ID for ties. a. Show the bookkeeping
Use the minimum slack heuristic to develop a resource schedule; use the smallest duration and then lowest activity ID for ties. a. Show the "bookkeeping" table presented in the class slides to develop the resource schedule. b. Which activities are now considered critical? c. What are the slack times for each of the non-critical activities