Question: Use the process information provided in the following table, when the sequence of flow is A - > B ( any machine can be used

Use the process information provided in the following table, when the sequence of flow is A -> B (any machine can be used if available)-> C -> D (any machine can be used if available).
Operation Number of Units of Equipment Design Capacity (by equipment) Planned Utilization (overall)
A 1240 units per hour 57.5%
B 4130,120,160,11082.0%
C 1250 units per hour 77.0%
D 2140,9562.5%
Calculate the maximum (design) capacity and effective capacity.
Note: Round "Effective capacity" to 2 decimal places.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!