Question: Use the process information provided in the following table, when the sequence of flow is A - > B ( any machine can be used

Use the process information provided in the following table, when the sequence of flow is A -> B (any machine can be used if available)-> C -> D (any machine can be used if available).
Operation Number of Units of Equipment Design Capacity (by equipment) Planned Utilization (overall)
A 1260 units per hour 87.5%
B 4110,100,140,9083.0%
C 1270 units per hour 65.0%
D 2160,11570.0%
Calculate the maximum (design) capacity and effective capacity.
Note: Round "Effective capacity" to 2 decimal places.