Use the project information contained in the attached Excel file to determine the initial: 1. Project duration
Question:
Use the project information contained in the attached Excel file to determine the initial:
1. Project duration & completion date
2. Critical path (CP)
3. Slack for activities not on the CP
Please use Excel to calculate using February 20, 2023 as the start date. (Check numbers: normal project duration is 73 days; normal/direct costs are $103,000. It is important to start from/use the correct starting points).
Apply schedule optimization techniques to reduce project duration to 68 days.Provide the process details for each crashing iteration: (1) activity shortened; (2) crash cost added; (3) new project duration; (4) new project cost; and (5) new critical path. Assume no fixed costs even though fixed cost are mentioned in the case.
Income Tax Fundamentals 2013
ISBN: 9781285586618
31st Edition
Authors: Gerald E. Whittenburg, Martha Altus Buller, Steven L Gill