Question: Use the project information in the table below to create a network diagram using Project Professional. Activity Predecessor Days to Complete 1 Contract Signoff -

Use the project information in the table below to create a network diagram using Project Professional.

Activity

Predecessor

Days to Complete

1

Contract Signoff

-

5

2

Art Design

1

4

3

Code Design

2

8

4

Database Design

2

6

5

Build Site

3,4

10

6

Test Site

5

9

7

UAT

6

12

8

User Signoff

7

3

9

Close Project

7,8

5

Question 1) What is the overall project duration?

Question 2) Name the activities that are on the critical path.

Question 3) What is the total slack time of the project? (Hint: slack time is the amount of time an activity can be delayed without delaying the project).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!