Question: Use the SPT rule. What is the average flow time and average tardiness? Job Job time Due Date (days) (days) A 14 20 B 10

Use the SPT rule. What is the average flow time
Use the SPT rule. What is the average flow time and average tardiness? Job Job time Due Date (days) (days) A 14 20 B 10 16 6 4 D 18 8 A. 20.5, 9 B. 20.5, 6.5 C. 20.5, 8 D. 20.5, 7