Question: 05 (15 pts.): Processing times (including setup times) and due dates for six jobs waiting to be processed at a work center are given in

05 (15 pts.): Processing times (including setup

05 (15 pts.): Processing times (including setup times) and due dates for six jobs waiting to be processed at a work center are given in the following table. a) Find job sequences by using the rules; FCFS, SPT, EDD and CR. (Note: Assume jobs arrived the order shown in the Table). b) Compare all job sequencing rules in terms of average flow time and average tardiness performance measures. Job Due Date (days from present time) A Processing Time (days) 2 8 4 B 7 16 4 D 10 17 E 15 5 12 F 18