Question: Use this scenario for the following question ( s ) . The process design team at a manufacturer has broken an assembly process into eight

Use this scenario for the following question(s).
The process design team at a manufacturer has broken an assembly process into eight
basic steps, each with a required time, and predecessor as shown in the table. There are
7.5 productive hours available in a day and the manufacturer wishes to produce 400 units.
Balance the line by assigning tasks to workstations to fill up as much takt time as possible.
Break ties by assigning the longest task first.
Refer to the scenario above. Without using more than one worker per station, what is the
maximum output achievable in the 7.5 hour work day?
1000 units
1800 units
1258 units
415 units
 Use this scenario for the following question(s). The process design team

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!