Question: Use this scenario for the next six questions. A project consists of the following activities: table [ [ Activity , Activity Predecessor,Time ( weeks

Use this scenario for the next six questions.
A project consists of the following activities:
\table[[Activity,Activity Predecessor,Time (weeks)],[A,--,8],[B,--,12],[C,A,B,4],[D,A,B,10],[E,C,7],[F,D,9],[G,E,F,8]]
Using the information in the table, the earliest finish (EF) time for activity D is
a.20 weeks
b.22 weeks
c.15 weeks
d.11 weeks
What is the Anount of slack associated with f
 Use this scenario for the next six questions. A project consists