Question: Using Excel and answer the questions below with the data provided: (Take answers out to the second decimal place) (13 pts.) Project Z Year CF
Using Excel and answer the questions below with the data provided: (Take answers out to the second decimal place) (13 pts.) Project Z Year CF 0-50 1 25 2 30 3 80 Calculate the payback period for Project Z year(s) (5 pts) Calculate the discounted payback period for Project Z when WACC is 12% years (8 pts)