Question: Using Excel. Given the estimated activity time below, and the longest time for a critical path as A - c - E - G ,

Using Excel. Given the estimated activity time below, and the longest time for a critical path as A-c-E-G, what is the critical path probability that the project will be completed within (based on the longest critical path)
Activity a m b
A 6.57.514.5
B 8.510.512.5
C 2.53.54.5
D 6.57.58.5
E 5.55.59.5
F 5.57.59.5
G 4.56.58.5
H 2.53.53.5
points
(a)21 days 1.4------------
(b)22 days 1.3-----------
(c)25 days1.3------------
----------------------
4 Total points

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!