Question: Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 B F D A E C 2 B F A E C

Using Johnson's rule for 2-machine scheduling, the sequence is:

Scheduled Order

Job

1

B

F

D

A

E

C

2

B

F

A

E

C

D

3

E

B

D

C

F

A

4

F

D

C

A

E

B

5

B

C

F

A

E

D

6

B

E

A

F

D

C

For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) =

nothing

hours (enter your response as a whole number).

.....

Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows:

Job

Operation 1 (hours)

Operation 2 (hours)

A

4

8

B

10

5

C

3

11

D

14

14

E

6

1

F

7

12

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!