Question: Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 B C A D E F Six jobs are to be processed
Using Johnson's rule for 2-machine scheduling, the sequence is:
| Scheduled Order | Job |
| 1 | B C A D E F |
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows:
| Job | Operation 1 (hours) | Operation 2 (hours) | ||
| A | 12 | 4 | ||
| B | 8 | 11 | ||
| C | 5 | 14 | ||
| D | 6 | 2 | ||
| E | 9 | 10 | ||
| F | 3 | 1 | ||
Click to select your answer(s) and then click Check Answer.
For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) =
hours (enter your response as a whole number
Step by Step Solution