Question: Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 B C A D E F Six jobs are to be processed

Using Johnson's rule for 2-machine scheduling, the sequence is:

Scheduled Order

Job

1

B

C

A

D

E

F

Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows:

Job

Operation 1 (hours)

Operation 2 (hours)

A

12

4

B

8

11

C

5

14

D

6

2

E

9

10

F

3

1

Click to select your answer(s) and then click Check Answer.

For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) =

hours (enter your response as a whole number

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!