Question: Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 A D E C B F 2 A E B C F
Using Johnson's rule for 2-machine scheduling, the sequence is:
| Scheduled Order | Job |
| 1 | A D E C B F |
| 2 | A E B C F D |
| 3 | E A B C F D |
| 4 | B E F D A C |
| 5 | A F B E D C |
| 6 | C E D A F B |
For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) =
enter your response here
hours (enter your response as a whole number).
.....
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows:
| Job | Operation 1 (hours) | Operation 2 (hours) | ||
| A | 12 | 4 | ||
| B | 8 | 11 | ||
| C | 5 | 14 | ||
| D | 6 | 2 | ||
| E | 9 | 10 | ||
| F | 3 | 1 | ||
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts