Question: Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 22months, and the
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 22months, and the project variance is 99. The probability that the project will miss a deadline of 24 months is (round your response to two decimal places). 0% 57.93% 50% 100% 42.07%
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts