Question: please explain how you found the answer without using excel. Using PERT, Adam Munson was able to determine that the expected project completion time for
Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 22 months, and the project variance is 16. a) The probability that the project will be completed in 6 months = (round your response to four decimal places)