Question: Using PERT, Ed Rose was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months and

Using PERT, Ed Rose was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months and the project variance is 4.

  1. What is the probability that the project will be completed in 17 months or less?
  2. The probability of the project being completed in less than 17 months is 0.02275.
  3. What is the probability that the project will be completed in 20 months or less?
  4. The probability of the project being completed in less than 20 months is 0.30854
  5. What is the probability that the project will be completed in 23 months or less?
  6. The probability of the project being completed in less than 23 months is 0.84134
  7. What is the probability that the project will be completed in 25 months or less?
  8. The probability of the project being completed in less than 25 months is 0.97725

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!