Question: Using PERT, Jane found out that the expected completion time for a research project 16 months, and the variance of this competition time is 6,

Using PERT, Jane found out that the expected completion time for a research project 16 months, and the variance of this competition time is 6, the probability that this project will be completed in 22 months is _