Question: Using PERT, the expected completion time to build a house is 70 days. The Standard Deviation of the project completion time is 4 days. What
Using PERT, the expected completion time to build a house is 70 days. The Standard Deviation of the project completion time is 4 days. What is the probability of completing the project within 66 days and within 78 days? What is the probability of completing the project after 78 days?
| 34% | ||
| 81% | ||
| 16% | ||
| 0% | ||
| 100% |