Question: Using production leveling, if the total demand was 20,000 units over a period of 3 months, and the 1st month had 20 days, the 2nd

Using production leveling, if the total demand was 20,000 units over a period of 3 months, and the 1st month had 20 days, the 2nd month 21 days, and the 3rd month 22 days, how much should the company produce each day to level production?