Question: Using Rule 50-50 and the attached figure, define the status of the project whether it is ahead or behind schedule: 5.000 TIME LINE 10.000 12.000
Using Rule 50-50 and the attached figure, define the status of the project whether it is ahead or behind schedule:

5.000 TIME LINE 10.000 12.000 LEGEND 3.000 COMPLETED 6.000 A NOT COMPLETED A6.000 9.000 TIME