Question: Question 1: 50/50 Rule Based on the above Gantt chart, the data given below, and by using the 50/50 rule - complete the Earned Value

 Question 1: 50/50 Rule Based on the above Gantt chart, the

Question 1: 50/50 Rule

Based on the above Gantt chart, the data given below, and by using the 50/50 rule - complete the Earned Value table for tasks A, C, F, J, K M and O.

Planned ValueActual CostsEarned ValueNotes.

Use the 50/50 rule to determine how much value was earned. Task A$3,000$1,000$3000$3000 x 100% = $3000. Task completed on time. Using to 50/50 rule, the value earned for this task is 100%Task C$10,000$7,000$10,000$10,000 x 100% = $10,000. Task completed one week over schedule. Using to 50/50 rule, the value earned for this task is 100%Task F$4,000$2,500$4000$4000 x 100% = $4000. Task completed ahead of schedule by two. Using the 50/50 rule, the value earned for this task is 100%Task J$6,000$2,000$3000$6000 x 50% = $3000. Task not completed to schedule. Therefore, using the 50/50 rule, this task has earned 50% value.Task K$8,000$7,000$4000$8000 x 50% = $4000. The task began ahead of schedule and is not completed. Therefore, using the 50/50 rule, this task has earned 50% value.Task M$3,000$3,500$3000$3000 x 100% = $3000. The task was started and completed ahead of schedule. The value earned for this task is 100% using the 50/50 rule.Task O$3,000$0$0$3000 x 0% = $0. This task is behind schedule and has not been started. Therefore, using the 50/50 rule the value earned is $0 because the task has not begun.

Question 2: Calculate Earned Value Indicators

Based on the following data:

The Budget At Completion (BAC) cost of the project is estimated to be: $52,250.

  • Earned value data is available for the first three weeks of the project (see below).
  • The project is due to end on week four (4).
Project DataWeek 1Week 2Week 3Week 4Cumulative Actual Costs

$5,000$16,000$37,800 Cumulative Planned Value$11,750$22,000$43,000$52,250Cumulative Earned Value$7,000$22,000$47,000

Based on the above data, calculate the following earned value indicators:

EVM IndicatorWeek 1Week 2Week 3Formula usedCost Variance

7000 5000

CV = $2000

22,000 16,000

CV = $6000

47,000 37,800

CV = $9200

CV = EV AC

Schedule Variance

7000 11,750

SV = -$4750

22,000 22,000

SV = 0

47,000 43,000

SV = $4000

SV = EV PVCost Performance Index

7000/5000

CPI = 1.4

22,000/16,000

CPI = 1.375

47,000/37,800

CPI = 1.2434

CPI = EV/AC

Schedule Performance Index

7000/11,750

SPI = 0.5957

22,000/22,000

SPI = 1

47,000/43,000

SPI = 1.093

SPI = EV/PV

Estimated Cost At Completion

(use the EAC = BAC / CPI formula)

52,250/1.4

EAC = $37,321.43

52,250/1.375

EAC = $38,000

52,250/1.2434

EAC = $42,021.87

EAC = BAC/CPI

Estimated Cost to Complete

37,321.43 5000

ETC = $32,321.43

38,000 16,000

ETC = $22,000

42,021.87 37,800

ETC = $4221.87

ETC = EAC AC

Question 3: Earned Value Management Dashboard

data given below, and by using the 50/50 rule - complete the

Question 4: Interpret the Projects Status

  1. What is the current week three (3) status of the project?
    • Is the project on schedule, behind schedule or ahead of schedule?
    • Is the project on budget, under budget or over budget?
  2. If progress continues at its current rate how much will the project likely cost?
    • Ensure that you reference the earned value terms and findings in your answer.

Legend: Planned Task Task has been completed (as of week 3) Tasks whose planned status does not its match actual status Tasks actual status New projected completion cilan narhhoned Legend: Planned Task Task has been completed (as of week 3) Tasks whose planned status does not its match actual status Tasks actual status New projected completion cilan narhhoned

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!