Question: Using Table 7 . 5 , every day the construction crew is on - site costs $ 1 0 0 0 . What activities would
Using Table every day the construction crew is onsite costs $ What activities would you consider crashing to reduce the project completion cost?
Select one:
A Activity
B Activity
C Activity G
D All of these activities would be candidates for crashing.