Question: Activity Predecessor Time ( days ) A - - 8 B - - 6 C - - 3 D A , B 1 0 E
Activity Predecessor Time days
A
B
C
D AB
E C
F A
G DE
H G
Using Table every day the construction crew is onsite costs $ What activities would you consider crashing to reduce the project completion cost?
Activity E
Activity F
Activity G
All of these activities would be candidates for crashing.